Yeah, I just for what just to clarify. The fiscal 24 budget which we went over a while back in terms of what was requested in the budget as you recall. We had the governor it through our budget preparation. There was a recommendation of $43 million. This is particularly for our augmenting needed infrastructure projects on Bell Island. One the legislature met and went through the process the what ended up coming out of the conference. Committee was $23 million, which is good. And they just let people know that the budget technically has not yet been signed. We're told that that'll likely happen by the end of the month or first of of August. But at any rate, these monies are coming from additional Recovery Act funds or ARPA funds if we refer to them of which we already have $12 million on Belisle that are involved with the conservatory and then the renovation to the casino building that you already got a briefing on. So so that's a lot of investment there. So at any rate, that 23 million, we're still working on figuring out the how that would be worked out one of the stipulations in the budget was that 10 million of that would be earmarked specifically which is part of what we had asked for, but to ensure that the HVAC air handling systems between the aquarium and the conservatory would be addressed. And so that definitely will get done that includes drainage work and stuff around the aquarium particularly so the basement doesn't flood and which is compromised a lot of different things including the the replacement heating system that got messed up when the floods came a couple of times and that's something that a lot of people don't see but it definitely is impacted a lot of stuff, even up to an including the bathroom in the aquarium. So at any rate, we're going to be so that's one piece and then the remaining money. We're trying to articulate how that would be divided out to so that we could still we have problems that you know we have to start down that road and renovate the fountain which as some of you might know that we had a valve valve problem with the that occurred last was four or five, six days ago I guess. And a valve and a four inch water line. That feeds the area down there didn't close properly and the de system for a sump pump. It's kind of complicated, but anyway, that one of the valves failed and it flooded the whole basement of it and water was coming out the door and so consequently all that new electrical stuff we just finished, got soaked and so we have added electricians in there working on that but that's a part of that is, you know, still some remnants of the old infrastructure that's in there and so at any rate it's not any bad hoping to get that thing back on track here but but the fact remains is that we need to start working towards that bigger fix, which some of you know, I guess everybody knows that the study that was done on the phone, show the cement, that was the original cement by the way in the early 1900s is starting to disintegrate and eventually the the leaking will start occurring more prolifically through the the pavement on the basin of the fountain and so that that has to be addressed and and then the modernization in some of the pumping systems and a lot of that stuff. So that's that's one and then we still have the we have the old zoo former zoo site and we want to invest in continuing to remove the the derelict buildings are not no longer used infrastructure there which we talked about to get that towards and start down the road to do the basically a first phase two and more naturalized that area per the studies and all that was done previously and then also we have some hazardous materials such as lead paint and asbestos and some of the other buildings that have to be addressed. So there was fun. There's that's a topic area and then the last bigger one was the the boathouse itself, which, as we all know is compromised and hasn't been habitable for quite some time and to have some resources to figure out what we do with that, cuz that is, as we've talked before, that is a issue and in and of itself and then collaborating with Detroit rowing group, which is have erected in in the process of temporary quarters to operate rolling and then of course, as you know, that at some point looping back on the master plan that they had presented before and things have changed. Obviously a lot with this boathouse situation, so that'll have to be addressed somehow in this process. And then the last thing that we do have some funds set aside in that to do some repurposing, planning to solidify the whatever, what, which pathway we'd end up solidifying regarding the the farmer zoo site, even though we do have a lot of good study work that was done by MSU and the other partners that were involved in that in the public input and then the, the trying to address to the US a couple of those spaces out there up to including the areas surrounding the boathouse, that front area, which is still compromised with the old infrastructure, the old former swimming pool and some of the other stuff that's out there, too. So and then one thing that that probably will have to come at a later time and that is dealing with the beach frontage. Because we had hoped to put in an alternative spray park for kids and do some renovation to the bathrooms and things but some, you know, so that is probably gonna have to be looked at but with the money being shrunk down to 23 million, which is a good thing. There's we can't do everything we had planned to do. Which then opens the other door. We met with the conservancy the other day and talking about now that we have this what potential there might be for leveraging philanthropic match funding and stuff like that. So that's a bit yet to be determined how that might work out, which would help, you know, try to bolster some of the funding that we had identified originally. So that's, that's kind of where we are with that. We should say that we did. We were successful and I want to emphasize the two that I mentioned, it's ARPA funds. That means that these funds as soon as the budgets done would be ready to be utilized because these are 2023. It's called a supplemental so those funds won't have to wait till October 1. So we can commence the process to figure out what what we will do and we'll have a better idea of that delineation of that once that once the budget is signed, and so in the next couple of months, we'll have that loop back and update people on what seems to make the most sense to press forward on but it's clearly the needs are right in front of us. The The other thing that as you know, due to the Grand Prix, leaving Belisle, we had the budget for Belle Isle was there was $450,000 that came from the revenue from that day was used for augmenting the operation. This is separate from the Grand premier funds. These are simply their permit fees and negotiated amount that they provided for capital improvements. And we were in the supplemental that was we were able to shore that up so our operating budget won't take a hit because of that. So that's that's a positive thing to keep. Keep the operational budget balanced with the loss of that revenue as you know, the any revenue generated on Belisle goes back to the operating budget in a restricted fund. And that would be that was a chunk there. So